World-class 100' × 200' clear-span Pre-Engineered Steel Rice Mill on a 200' × 400' industrial plot — engineered with 9" brick dado walls, raised RCC pedestals, 7" M30 industrial concrete flooring, and a 150 kWp solar power plant.
Every aspect of the solar installation is illustrated below — from the non-penetrating rooftop mounting of 250 Tier-1 panels to the dual 75 kW IP65 inverters and FESCO Net-Metering room.
Occupies ~6,925 sq. ft. of the 21,000 sq. ft. roof slope, preserving gravity ridge ventilators and maintenance walkways, while PEB rafters carry +4.0 psf solar collateral load across the entire roof.
ROOFTOP ARRAY // 250 PANELS
Anodized 6005-T5 aluminum clamps lock directly onto the roof ribs without drilling a single hole—guaranteeing zero monsoon roof leaks and 140 km/h wind uplift resistance alongside the continuous gravity ridge ventilator.
INVERTERS & NET-METERING
Two IP65 outdoor/indoor-rated 75 kW 3-phase string inverters with multi-MPPT tracking, DC Type-II surge arrestors, DC isolator boxes, <10 Ω dedicated earthing pits, and bi-directional FESCO net-metering export.
Designed by Pakistani Rice Mill Process Specialists for 5–15 TPH automated Basmati & IRRI milling lines, eliminating moisture loss and dust/fire hazards.
BAY 1–4 MILLING FLOW
ATEX / NFPA-61 SAFETY
200' × 400' MASTERPLAN
Engineered for Faisalabad alluvial soil (qa = 1.25 TSF) and Seismic Zone 2A, with Finished Floor Level (FFL) raised +2'-0" above Natural Ground Level (NGL) for flood immunity.
BRICKWALLS // 552 RFT × 9'
Protects lower PEB cladding from paddy heaps and forklift impact: 9" thick Awwal burnt clay brick masonry (9'-0" high above FFL) with 13.5"×18" pilasters @ 12'-6" c/c, 2" PCC + bitumen DPC, two 9"×6" RCC tie bands (@ +4' & +9'), and 1:4 waterproofed plaster.
COLUMNS & PEDESTALS
18 main pad footings (6'×6'×1'-6") + 2 gable footings (4'-6"×4'-6"×1'-3") on 3" lean concrete. 20"×20" raised M25/M30 pedestals (+2'-6" above FFL, 8-#6 bars) with 116 Nos. M24/M30 Gr. 8.8 anchor bolts, 25mm baseplates, 1.5" non-shrink grout, and 600 RFT plinth beams.
CONCRETE FLOOR // 20,000 SFT
6" WBM granular sub-base (98% MDD) + 200-μm LDPE vapor barrier + 7" (175mm) M30 (4,000 psi) concrete reinforced with #4 Gr. 60 rebar mesh @ 8" c/c and #5 dowels, broadcast with 4.5 kg/m² quartz hardener, power-troweled, and saw-cut at 15'×15' PU-sealed joints.
Compare the insulated sandwich-panel option against single-skin PPGI sheeting below. Both packages include the Solar-Ready PEB steel frame, RCC foundations, pedestals, and industrial concrete floor.
OPTION A // 50MM PU SANDWICH
OPTION B // PPGI SHEETING
Complete structural steel, envelope, and civil foundation schedule for the 100' × 200' (20,000 Sq. Ft.) Rice Mill Factory. All pricing is blurred pending commercial review.
| Code | Scope / Component | Engineering Specification | Qty / Unit | Amount (PKR) |
|---|---|---|---|---|
| A1 | Primary Structural Framing | Built-up tapered I-sections (ASTM A572 Gr.50), 100' clear span, 20' eave, 35' ridge, +4 psf solar collateral load. | 40,000 KG | 13,400,000 |
| A2 | Secondary Framing & Bracing | Pre-galvanized 200mm Z-purlins (275 g/m²), wall girts, gable posts, sag rods & diagonal wind bracing. | 10,500 KG | 3,255,000 |
| A3 | Plates, Anchor & HSFG Bolts | 25mm base/splice plates (~4,000 KG), 116 Nos. M24/M30 Gr. 8.8 anchor bolts & HSFG splice bolts. | 1 Lot | 1,450,000 |
| A4 | Fabrication & Epoxy Coating | CNC cutting, SAW welding, ISO 8501-1 prep, 2 coats Zinc-Phosphate Epoxy Primer + enamel topcoat. | 54,500 KG | 1,907,500 |
| A5 | Freight, 50T Crane & Erection | Delivery to Faisalabad site, 50-Ton mobile craneage, rigging & certified erection crew. | 20,000 SFT | 2,300,000 |
| SUBTOTAL PART A — PEB STRUCTURAL STEEL FRAME (SOLAR-READY) | PKR 22,312,500 | |||
| B-A | Envelope Option A (Sandwich Panel) | 50mm PU/PIR Sandwich Panels on Roof (~21,000 sft) & Walls (~12,500 sft) + GI gutters, downspouts & skylights. | 33,500 SFT | 31,270,000 |
| B-B | Envelope Option B (PPGI Sheeting) | 0.50mm PPGI/Zincalume Roof (~21,000 sft) & 0.45mm PPGI Walls (~12,500 sft) + ridge vents, gutters & skylights. | 33,500 SFT | 10,190,000 |
| C1 | RCC Footings, Pedestals & Plinth | 20 Nos. RCC isolated pad footings, 20"×20" raised pedestals (+2'-6" FFL), 600 RFT 12"×18" plinth beams (7.40 MT Gr. 60). | 1 Lot | 6,850,000 |
| C2 | 9" Brick Dado Perimeter Wall | 552 RFT × 9'-0" First-Class brick masonry (50,000 bricks), 13.5"×18" pilasters, DPC, 2 RCC bands & 1:4 plaster. | 3,500 CFT | Included |
| C3 | Industrial Concrete Floor Slab | 6" GSB (98% MDD), 200-μm barrier, 7" M30 reinforced concrete slab (20.40 MT mesh), quartz hardener & 15'×15' PU joints. | 20,000 SFT | 10,500,000 |
| C4 | Industrial Shutters & Exit Doors | Heavy-duty truck rolling shutters + steel fire/personnel exit doors. | 1 Lot | 1,150,000 |
| SUBTOTAL PART C — CIVIL FOUNDATIONS, INDUSTRIAL FLOOR & DOORS | PKR 18,500,000 | |||